Development Secretary Bernadette Linn (甯漢豪) spoke on 13 November 2026 at a special meeting of the Legislative Council Panel on Development about the lift installation works at Clinical Block 1 of the new Queen Mary Hospital building. She said primary responsibility lay with the contractor and the lift subcontractor, while the professionals and government staff charged with oversight also fell short in management and supervision.
The building has 28 lifts and was built by the Architectural Services Department. Its main works were largely finished in early 2025 and the block is still being tested and rectified. The government said it was unusual that several lifts kept breaking down after the main works were largely complete. The building is not yet fully in use, although some non-clinical facilities, including a restaurant, a convenience store and a laboratory, have opened.
Investigation and causes of the faults
The Development Bureau stepped in at the request of the Health Bureau in April 2026, began its investigation in September that year and has submitted a report to the Chief Executive.
The government announcement lists four causes. First, the dimensions and verticality of the lift shaft walls deviated, narrowing the space around components. Second, guide rails on different floors were not aligned in a straight line. Third, the weight of the lift car was unevenly distributed. Fourth, the registered lift contractor's workmanship fell short of standard, and some components, after repeated adjustment, sat at the limit of permitted tolerance.
Shortcomings identified by the government
- The contractor and subcontractor carried out installation work inaccurately and did not follow it up properly.
- Gaps in the contractor's inspection, testing and approval checklist were left unaddressed.
- Supervision and acceptance checks were inadequate.
- Architectural Services Department staff were negligent when issuing the building completion certificate.
- The Electrical and Mechanical Services Department's procedures and practices for issuing lift permits were deficient.
The government does not regard the matter as systemic but says the current system can be improved. RTHK's report of the same day carries the same account from Linn, saying the contractor and subcontractor failed in their duties and that the supervising staff were also lacking in management.
Disciplinary action and criminal referral
The Development Bureau recommended that the Director of Architectural Services open disciplinary investigations into the government staff involved. The final outcome depends on the proceedings, which include giving those concerned a chance to respond. The government will also start disciplinary proceedings against the contractor, subcontractor, consultants and professionals under the applicable regulatory regimes, and some aspects that may involve criminal elements have been referred to law enforcement agencies.
Improvements and opening timetable
The Architectural Services Department has tightened lift inspection procedures, increased on-site testing and upgraded its digital works supervision system, while the Electrical and Mechanical Services Department has stepped up patrols and spot checks. The latter is also conducting a comprehensive review of lift installation, inspection, maintenance and site supervision, and of the registration, regulation and approval system under the Lifts and Escalators Ordinance, due to finish by the end of 2026.
The government acknowledged that the building's full opening has been delayed, but said lift repairs are progressing well and are being handed over to the hospital in stages. The remaining repairs are expected to finish in the fourth quarter of 2026, after which the hospital can take over and prepare for the building's opening.
News reporting only. Not investment advice.